We built a house
I wanted to build a simple yet durable house. I especially wanted something that could ride out another typhoon Haiyan/Yolanda. I've been tinkering with a hexagonal design for a couple of years. It's just two stories with 160 square meters interior space. I cleaned up my simple unprofessional drawings, and took them to a real engineering construction company to get an estimate.
They could build the entire project for about 4.5 Million Pesos. This is more than I wanted to spend, so I built it myself.
I hired an independent engineer to draw up the construction plans. I hired the crew myself. I sourced and purchased all the materials, and I did it all for 1.8 Million Pesos.
It took 7 months.
I love my new house. It is awesome.
2 story concrete house | ||||
160 square meters | ||||
Designed to be proof to all but apocalyptic earth quake and typhoon | ||||
Project expenses | ALL in PESOS | |||
04/23/15 | Plans | $10,000 | Civil engineer, John | |
05/07/15 | Plans part 2 | $10,000 | Civil engineer, John | |
05/08/15 | blue prints | $900 | NLDT | |
05/09/15 | plumber sign off | $2,500 | Filiman | |
05/09/15 | electrician sign off | $2,500 | Filiman | |
06/01/15 | coco lumber | $30,000 | barangy Cpt. Bro | |
06/04/15 | ReBar Cement(350bags) CHB(2850blocks) etc... | $448,470 | Margie Grace | |
06/05/15 | structural analysis | $1,000 | Civil engineer, John | |
06/08/15 | 16m3 fine sand | $16,000 | LAP hardware | |
06/09/15 | 16m3 gravel | $16,000 | LAP hardware | |
06/09/15 | nails | $2,200 | LAP hardware | |
06/10/15 | Permits | $4,400 | Biliran | |
06/11/15 | Angle grinder | $5,600 | Brodeth | |
06/15/15 | cutting wheels | $1,000 | ||
06/16/15 | bender | $500 | welder | |
06/18/15 | LABOR | $14,350 | includes cistern | |
06/23/15 | Boulders – 2m3 | $2,000 | barangy Cpt. Bro | |
06/24/15 | insecticide | $3,500 | Margie Grace | |
06/25/15 | nails | $300 | LAP hardware | |
06/26/15 | coco lumber | $3,456 | barangy Cpt. Bro | |
06/27/15 | plumbing supplies | $21,655 | Margie Grace | |
06/27/15 | drill | $5,200 | Margie Grace | |
06/27/15 | LABOR | $21,675 | ||
07/04/15 | bath room set | $6,300 | Margie Grace | |
07/04/15 | electrical supplies | $53,370 | Limpiado | |
07/04/15 | LABOR | $23,400 | ||
07/04/15 | coco lumber | $7,290 | barangy Cpt. Bro | |
07/04/15 | LABOR | $9,000 | Electrical | |
07/06/15 | gravel 10m3 | $12,000 | Lilia Hardware | |
07/06/15 | gravel 8m3 | $10,400 | barangy Cpt. Bro | |
07/09/15 | Sand 8m3 | $10,400 | barangy Cpt. Bro | |
07/11/15 | LABOR | $24,650 | ||
07/12/15 | plywood, tie wire | $5,470 | Margie Grace | |
07/16/15 | LABOR | $6,000 | Electrical | |
07/17/15 | LABOR | $21,790 | ||
07/20/15 | Cement(100) | $27,250 | Margie Grace | |
07/23/15 | Sand 8m3 | $10,400 | barangy Cpt. Bro | |
07/29/15 | plywood, nails | $2,400 | Margie Grace | |
07/30/15 | LABOR | $2,000 | Electrical | |
08/01/15 | LABOR | $14,500 | ||
08/06/15 | shower and drawers | $9,500 | Brodeth | |
08/08/15 | LABOR | $8,600 | ||
08/12/15 | sahara and tie wire | $3,880 | Margie Grace | |
08/12/15 | water tank | $9,830 | Brodeth | |
08/15/15 | LABOR | $15,950 | ||
08/16/15 | LABOR | $3,000 | Electrical | |
08/18/15 | Sand 8m3 | $10,400 | sand man | |
08/18/15 | LABOR | $5,360 | temp labor | |
08/19/15 | LABOR | $3,000 | Electrical | |
08/21/15 | tie wire | $1,890 | Margie Grace | |
08/22/15 | 14' truss | $4,070 | lumber yard | |
08/22/15 | front door | $6,300 | Margie Grace | |
08/22/15 | lumber for roof | $2,188 | Margie Grace – P26040 16mm rebar refund | |
08/22/15 | LABOR | $18,250 | ||
08/24/15 | Door knob | $5,085 | Brodeth | |
08/24/15 | color metal roof | $48,170 | Margie Grace | |
08/26/15 | sewer pipes | $1,740 | Margie Grace | |
08/28/15 | pipes | $3,340 | Margie Grace | |
08/29/15 | LABOR | $11,775 | ||
08/29/15 | electrical conduit | $1,300 | Margie Grace | |
08/29/15 | LABOR | $3,000 | Electrical | |
09/02/15 | LABOR | $2,000 | Electrical | |
09/03/15 | Gravel 4m3 | $4,800 | Sulla Hardware | |
09/03/15 | LABOR | $9,325 | ||
09/16/15 | Sand 8m3 | $10,400 | Sulla Hardware | |
09/17/15 | Cement(100) & electrical | $31,650 | Margie Grace | |
09/18/15 | Shower | $1,500 | Brodeth | |
09/19/15 | LABOR | $11,550 | ||
09/22/15 | hollow block 500 | $6,500 | Sulla Hardware | |
09/23/15 | rivits and misc. | $1,610 | Margie Grace | |
09/26/15 | LABOR | $13,850 | ||
09/27/15 | LABOR | $1,500 | Electrical | |
09/30/15 | sand 4m3 + grind wheels | $5,825 | Sulla Hardware | |
10/03/15 | LABOR | $11,850 | ||
10/06/15 | Cement 100 | $24,000 | Margie Grace | |
10/08/15 | sinks | $6,213 | Brodeth | |
10/08/15 | bathroom fixtures | $760 | Margie Grace | |
10/10/15 | LABOR | $15,300 | ||
10/11/15 | waterproofing + misc | $2,435 | Margie Grace | |
10/13/15 | sand 8m3 | $10,400 | Sulla Hardware | |
10/13/15 | tile | $74,560 | Naval Tile | |
10/15/15 | waterproofing | $4,560 | paint store | |
10/16/15 | diamond wheel | $300 | ||
10/17/15 | doors | $18,200 | Margie Grace | |
10/17/15 | bath room tile | $13,000 | Margie Grace | |
10/17/15 | LABOR | $12,350 | ||
10/20/15 | misc | $660 | Margie Grace | |
10/22/15 | hollow block 80 | $1,120 | Sulla Hardware | |
10/24/15 | LABOR | $16,300 | ||
10/26/15 | lumber for ceiling | $31,000 | lumber yard | |
10/26/15 | plywood for ceiling | $45,000 | Margie Grace | |
10/29/15 | light fixtures | $8,040 | Brodeth | |
10/29/15 | Cement 100 | $23,500 | ||
10/30/15 | light fixtures | $1,120 | Margie Grace | |
10/31/15 | LABOR | $15,500 | ||
11/02/15 | nails | $140 | Margie Grace | |
11/03/15 | sand 8m3 | $10,400 | Sulla Hardware | |
11/06/15 | hinges | $800 | ||
11/07/15 | cutting wheel & nails | $610 | Margie Grace | |
11/07/15 | LABOR | $12,750 | ||
11/08/15 | door knobs & lamps | $7,100 | Margie Grace | |
11/10/15 | windows | $65,628 | Gemar glass | |
11/11/15 | curtain rods | $1,498 | Gemar glass | |
11/11/15 | toilet | $4,780 | Margie Grace | |
11/13/15 | light bulbs | $2,260 | Margie Grace | |
11/14/15 | LABOR | $15,550 | ||
11/16/15 | Bulbs & electrical | $2,600 | Margie Grace | |
11/18/15 | plumbing | $2,224 | Brodeth | |
11/20/15 | electrical | $700 | ||
11/20/15 | sand 4m3 | $5,200 | Sulla Hardware | |
11/21/15 | LABOR | $10,775 | ||
11/25/15 | tile | $9,585 | Naval Tile | |
11/25/15 | plumbing | $291 | Brodeth | |
11/26/15 | Cement 20 | $5,300 | Margie Grace | |
11/26/15 | Bath room fixtures | $8,272 | Brodeth | |
11/26/15 | curtains | $2,652 | ||
11/27/15 | cutting wheels | $1,100 | Margie Grace | |
11/28/15 | LABOR | $15,000 | ||
12/01/15 | hollow block 100 | $1,350 | Sulla Hardware | |
12/03/15 | Cement 18 | $4,890 | Margie Grace | |
12/05/15 | LABOR | $14,850 | ||
12/04/15 | cabinet supplies | $13,495 | Margie Grace | |
12/07/15 | LABOR | $2,000 | Electrical | |
12/08/15 | cabinet supplies | $4,050 | Margie Grace | |
12/10/15 | cabinet supplies | $6,765 | Margie Grace | |
12/10/15 | bar stool | $1,400 | ||
12/12/15 | LABOR | $10,050 | ||
12/13/15 | LABOR | $2,500 | Electrical | |
12/14/15 | paint | $12,000 | ||
12/15/15 | paint | $1,915 | ||
12/15/15 | plumbing | $700 | Margie Grace | |
12/16/15 | shelving | $500 | Margie Grace | |
12/17/15 | misc | $355 | ||
12/19/15 | as built electrical plan | $5,000 | Filiman | |
12/19/15 | paint | $18,990 | ||
12/19/15 | LABOR | $11,850 | ||
12/20/15 | stove, fans | $6,000 | Prince | |
12/23/15 | paint | $5,044 | ||
12/26/15 | LABOR | $6,275 | ||
01/02/16 | paint | $805 | ||
01/02/16 | LABOR | $8,750 | ||
01/05/16 | bars and awnings | $30,000 | ||
01/07/16 | LABOR | $5,500 | ||
Total | $1,843,381 | |||
Summary: | ||||
Pesos | ||||
Bags of cement | 768 | @ aprox P240 per bag | 184,320 | |
Hollow blocks | 3530 | @ aprox P15 ea | 52,800 | |
sand and gravel m3 | 104 | @ aprox P1300 ea | 135,200 | |
coco lumber | for scaffolding | 41,000 | ||
rebar | 10, 12, & 16mm | 291,800 | ||
plywood for forms | 40 | @330 sheet | 20,200 | |
wood for ceiling | 76,000 | |||
tile | 97,560 | |||
windows | 67,000 | |||
LABOR | 430,675 | |||
Total | 1,396,555 | |||
Other/misc | 446,826 | |||
Total | 1,843,381 | |||
ALL in PESOS | ||||
06/18/15 | LABOR | $14,350 | cistern | |
06/27/15 | LABOR | $21,675 | ||
07/04/15 | LABOR | $23,400 | ||
07/04/15 | LABOR | $9,000 | Electrical | |
07/11/15 | LABOR | $24,650 | ||
07/16/15 | LABOR | $6,000 | Electrical | |
07/17/15 | LABOR | $21,790 | ||
07/30/15 | LABOR | $2,000 | Electrical | |
08/01/15 | LABOR | $14,500 | ||
08/08/15 | LABOR | $8,600 | ||
08/15/15 | LABOR | $15,950 | ||
08/16/15 | LABOR | $3,000 | Electrical | |
08/18/15 | LABOR | $5,360 | temp labor | |
08/19/15 | LABOR | $3,000 | Electrical | |
08/22/15 | LABOR | $17,250 | ||
08/29/15 | LABOR | $11,775 | ||
08/29/15 | LABOR | $3,000 | Electrical | |
09/02/15 | LABOR | $2,000 | Electrical | |
09/03/15 | LABOR | $9,325 | ||
09/19/15 | LABOR | $11,550 | ||
09/26/15 | LABOR | $13,850 | ||
09/27/15 | LABOR | $1,500 | Electrical | |
10/03/15 | LABOR | $11,850 | ||
10/10/15 | LABOR | $15,300 | ||
10/17/15 | LABOR | $12,350 | ||
10/24/15 | LABOR | $16,300 | ||
10/31/15 | LABOR | $15,500 | ||
11/07/15 | LABOR | $12,750 | ||
11/14/15 | LABOR | $15,550 | ||
11/21/15 | LABOR | $10,775 | ||
11/28/15 | LABOR | $15,000 | ||
12/05/15 | LABOR | $14,850 | ||
12/07/15 | LABOR | $2,000 | Electrical | |
12/12/15 | LABOR | $10,050 | ||
12/13/15 | LABOR | $2,500 | Electrical | |
12/19/15 | LABOR | $11,850 | ||
12/26/15 | LABOR | $6,275 | ||
01/02/16 | LABOR | $8,750 | ||
01/07/16 | LABOR | $5,500 | ||
$430,675 |